rabbit994

rabbit994 t1_iu2ryve wrote

> I was surprised that GCP is losing 600mil/quarter. Either they have crazy scaling happening or something terrible is happening cost wise.

Datacenter build out and massive discounts to major companies to sign them up. I worked at a company that was dragged into GCP by our CTO and part of the reason was massive discount GCP gave us. Generally everything was half off list price with some stuff higher than that.