100% agree. Terrible time to replace asphalt right now due to cold temps. Asphalt plants open during the day only so contractors cant get any at night when the do some of their work. The concrete they put in is supposed to be to the top of the trench so they can mill it down when they come back with the top coat of asphalt.

The trench this contractor dug in OP's image is probably for water or gas. The contractor is likely responsible to mill the lane they worked thru and either ran out of time or money.