Willie_the_Wombat t1_j06wu6f wrote
Reply to comment by Elegant_Schedule1566 in How much did it cost you to run power to your build per foot/yard? Green Mountain Power by Elegant_Schedule1566
Yes, back when I was an apprentice. We attached conduit to the bottom of a covered bridge at a winery.
You (or your contractor) will be responsible for installation of the primary conduit run in whatever path it takes. But your utility (GMP or others) will design that installation for you. Primary (before the final transformer) is outside the jurisdiction of the NEC and local inspectors if applicable. The utility will specify what conduit(s), cover, attachments, etc… for you depending on the particulars of your project.
Elegant_Schedule1566 OP t1_j06xtx9 wrote
Gotcha, thanks a ton man. Very helpful.