Viewing a single comment thread. View all comments

Status_Silver_5114 t1_j4dzorh wrote

Reply to comment by Ryland42 in Solar panels by DogGroundbreaking568

We used solpower too and highly rec. the wait for us was more the state inspector (6 weeks post installation). But totally worth it.

2

Ryland42 t1_j4e1a23 wrote

It took them 6 months from down payment to system install. The inspections and connection was a week.

1

Status_Silver_5114 t1_j4e1jqx wrote

Our inspection took much longer - could have been time of year? This was also 2016……. Our install was about 3 months from contract > install.